2024 and 2025 Street Surface Seal Project (Area 5 & 1)

2025 Street Surface Seal Project

Project Highlights

  • Combines the 2024 and 2025 Street Surface Seal Projects
  • Focus on Areas 5 (Avalon-Brentwood) & Area 1 (Westborough)
  • Includes surface seal and pavement markings
  • Construction start date: August 13, 2025

The 2025 Street Surface Seal Project combines the 2024 and 2025 Street Surface Seal Projects focusing on Areas 5 & 1.

PMP Schedule Map 2025-2029_05.2025.jpg

Next Steps: Surface Seal Application

Phase 1 (Base Repairs) began mid-July and focused on repairing localized asphalt failures.

Phase 2 (Striping and Pavement Markings Removal and Crack Seal) will run throughout the month of August 2025 into September 2025.

Phase 3 (Surface Seal) will follow Phase 2 and run through the month of October. This phase includes:

  • Surface Seal Application
  • Installing New Striping and Pavement Markings

Interactive Map

Click the link below to explore the Surface Seal Schedule Map and view layers for the 2024 and 2025 projects.

    INTERACTIVE MAP     

Full Surface Seal Application Schedule

Click below to download the detailed weekly schedule map showing planned work by street and date.

Weekly Schedule Map (PDF)(PDF, 39MB)

Weekly Schedule Excel(PDF, 83KB)

Translated Flyers

Spanish(PDF, 3MB)

Tagalog(PDF, 3MB)

Chinese(PDF, 3MB)

Contact: Project Manager, Lawrence Henriquez, Senior Civil Engineer — 650-829-6652