The 2025 Street Surface Seal Project combines the 2024 and 2025 Street Surface Seal Projects focusing on Areas 5 & 1.
Next Steps: Surface Seal Application
Phase 1 (Base Repairs) began mid-July and focused on repairing localized asphalt failures.
Phase 2 (Striping and Pavement Markings Removal and Crack Seal) will run throughout the month of August 2025 into September 2025.
Phase 3 (Surface Seal) will follow Phase 2 and run through the month of October. This phase includes:
- Surface Seal Application
- Installing New Striping and Pavement Markings
Interactive Map
Click the link below to explore the Surface Seal Schedule Map and view layers for the 2024 and 2025 projects.