Dundee Park Playground Improvements

Dundee Park Playground Improvements

Project Overview

Playground improvements are planned for Dundee Park.

Project Scope

Scope of work includes:

  • Replace Playground
  • Site Access / Paving
  • Court Improvements
  • Landscape Improvements
  • Ongoing improvements

Project Budget

The total project budget for design and construction is $600k.

Proposed Schedule

  • City Council approval in Jan/Feb 2025
  • 8 months of construction
  • Opening late 2025

 

Project Updates

Survey Results - 7/23/25

Thank you to everyone who completed the survey!

After reviewing the survey results and comments, we prepared a summary of findings and provided direction to the design team.

SURVEY RESULTS

  • Similar to the April 14 Community Workshop, there was overall support for the park improvements, including the addition of a picnic area and the leveling of the sport court.
  • There were some inquiries about barbecues. Parks staff is concerned about the litter and fire risk created by installing permanent barbecues.
  • Some neighbors requested a dog play area but there is no feasible space within the park for a dedicated dog area.
  • More sitting areas were requested – these are not shown in the drawings but will be added in their existing location along Dundee Drive.
  • Street lighting is an issue that we will review with the Public Works Department.
  • Better shade will be created with additional tree planting and the coverage of integral shade elements on the playground components.
  • There were concerns about court conflicts between basketball users and trike/bike/scooter users. Having a multiple use court has worked in other parks and are typically used on a first-come, first-served basis.

PLAYGROUND

  • Option 2 was preferred over option 1, but there were several requests to combine the best features of both designs.
  • Given the small size of the park, there is a general feeling of maximizing the play elements within the footprint of the playground.
  • There is support for both the balloon playground but also the sail playground, so the landscape architect has used one of each as shown in the below images.
  • Bright and light colors were popular.
  • Toddler swings instead of a group swing is preferred due to safely concerns and a need to focus on younger children.

CURRENT STATUS

We are waiting for pricing from the contractor. We hope to attend the August 19 Parks and Recreation Commission meeting to provide an update on design and construction. If the construction costs are negotiated within the next two weeks, we plan to bring the project to City Council for award on August 27, which would allow construction to start in October. We will provide more updates as they become available.

Open House - 4/14/25

Stop by to learn about the park and offer your ideas for what playground elements you prefer! 

If you cannot make the meeting, please click here to take the survey.

Dundee Park Open House flyer Dundee Park Open House flyer in Spanish

Community Meeting - 10/7/24

Thanks to all who attended Community Meeting #1 for the Dundee Park Playground Improvements Project. See links below for Meeting #1 materials.

Dundee Park Community Meeting flyer Mejoras al Parque Dundee reunión comunitaria

 

Additional Information

Get Updates

Sign up to receive updates about this specific project at our newsletter subscribe page.

Contact

For additional questions or information that is not listed here, please email parkprojects@ssf.net and a staff member will respond to you.

Location

Dundee Dr and Mansfield Dr,  94080  View Map